Legislation Details

File #: 1655    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 10/27/2026 In control: Governing Board
On agenda: 11/5/2026 Final action:
Title: Presentation, discussion, and possible action on a request for return and reallocation of tax credits under 10 TAC §11.6(5) related to Credit Returns Resulting from Force Majeure Events for Town East Trails
Sponsors: Cody Campbell
Attachments: 1. Town East Trails FM Request (Flattened), 2. Town East Trails Construction Schedule (Flattened), 3. Town East Trails REA Report (Flattened)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Presentation, discussion, and possible action on a request for return and reallocation of tax credits under 10 TAC §11.6(5) related to Credit Returns Resulting from Force Majeure Events for Town East Trails

end

RECOMMENDED ACTION

recommendation

WHEREAS, the above listed development was awarded 9% housing tax credits during the 2023 competitive Application round;

WHEREAS, staff executed a Carryover Allocation Agreement with the Development Owner, which included certifications from the Development Owner that each building for which the allocation was made would be placed in service by December 31, 2025;

WHEREAS, the Board approved a request for force majeure treatment in 2025, that extended the deadline to be placed in service to December 31, 2026;

WHEREAS, the Applicant has requested that the Board grant approval to allow for an additional 90 days;

NOW, therefore, it is hereby

RESOLVED, the requests for treatment under an application of the force majeure rule are approved, with the 2023 Qualified Allocation Plan and Uniform Multifamily Rules, and the 2026 Program Calendar applicable to the Development, except that the deadline to place in service is March 31, 2027.

end

BACKGROUND

Town East Trails is a 76-unit New Construction Development that is nearing completion in Mesquite. The project was awarded Housing Tax Credits in 2023. For an award of 9% housing tax credit, the Applicant has until the end of the second calendar year following the award to complete construction and place the buildings in service, otherwise, the project is not eligible to claim its Tax Credits. The initial deadline for this project was December 31, 2025., but Board approval of a reallocation of the credits in 2025 has resulted in a deadline to place in service of December 31, 2026 (this process is established in the QAP and is colloquially referred to as “force majeure treatment”).

The project is nearing completion and is currently on track to meet its existing deadline.  The developer explains the current status of the project and the rationale for the extension in the request:

Although we still expect the construction to be completed by the original Place in Service deadline of 12/31 2026, it's very unlikely we will receive the Certificate of Occupancy (CofO) from the City of Mesquite before the current Placed in Service deadline. The City of Mesquite will not issue a CofO until the elevator passes a Texas Department of Licensing and Registration (TDLR) state inspection, but the lead time for inspectors is two to five weeks after the elevator is installed. We are hoping that the elevator installation will be completed and operational by the third week of December if the current schedule holds. This creates a severe compliance risk given the end of year holidays since we are unlikely to be able to get a state elevator inspector onsite before the end of 2026. There is also concern that even if we were to get a passing elevator inspection from the state inspection before the end of 2026, the City of Mesquite may not have staff available at the end of December to be able to issue the CofO.​

Because of these delays, the Owner is requesting a 90-day extension of the placed-in-service date, to March 31, 2027.

Because the Development is finalizing construction completion, staff recommends the Board approve the request.