Title: Presentation, discussion, and possible action on a request for an extension of the previously approved deadline to Place in Service for Commons at St. Anthony's
Sponsors: Cody Campbell
Attachments: 1. Commons at St Anthonys Extension Request (Flattened)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Presentation, discussion, and possible action on a request for an extension of the previously approved deadline to Place in Service for Commons at St. Anthony's

end
RECOMMENDED ACTION

recommendation
WHEREAS, the above listed development was awarded 9% housing tax credits during the 2020 competitive Application round;

WHEREAS, staff executed a Carryover Allocation Agreement with the Development Owner, which included certifications from the Development Owner that each building for which the allocation was made would be placed in service by December 31, 2022;

WHEREAS, the Board previously approved a request for force majeure treatment in 2021, that extended the deadline to be placed in service to December 31, 2023;

WHEREAS, the Board previously approved a request for force majeure treatment in 2022, that extended the deadline to be placed in service to December 31, 2024;

WHEREAS, the Board previously approved a request for force majeure treatment in 2024, that extended the deadline to be placed in service by six months to June 30, 2025, which is considerably earlier than the allowable federal deadline of December 31, 2026;

WHEREAS, in May 2025, the Board extended that previously approved deadline to December 31, 2025, which is still earlier than the allowable federal deadline of December 31, 2026; and

WHEREAS, the Applicant has requested that the Board grant an approval to allow for an additional 90 days;

NOW, therefore, it is hereby

RESOLVED, that the previously approved deadline to place in service for Commons at St. Anthony's is approved to now be March 31, 2026.

end

BACKGROUND

Commons at St. Anthony's is a 124-unit Adaptive Reuse Development that is nearing completion in Amarillo. The project proposes the conversion of a vacant hospital in Amarillo into a Development for seniors. The project was awarded Housing Tax Credits in 2020. For an award of 9% housing tax credit, the Applicant has until the end of the second calendar year followi...