Skip to main content
File #: 666    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 6/3/2024 In control: Governing Board
On agenda: 6/13/2024 Final action:
Title: Presentation, discussion, and possible action on extensions of the development periods for Sierra Vista and Eastern Oaks
Sponsors: Connor Jones
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Presentation, discussion, and possible action on extensions of the development periods for Sierra Vista and Eastern Oaks
end
RECOMMENDED ACTION
recommendation
WHEREAS, Riverside Senior Investments, LP (Owner) is a prior Neighborhood Stabilization Program (NSP) recipient and Owner of Sierra Vista Senior Villas that provides 272 affordable Units in Fort Worth, Tarrant County;
WHEREAS, the Department and Owner executed a contract for these funds on February 15, 2019, and that contract includes a specific development period;
WHEREAS, in accordance with and pursuant to 10 TAC ?11.207 and 10 TAC ?13.1(c), on September 1, 2022 the Board approved a waiver of 10 TAC ?13.11(m) (re-codified and currently cited as 10 TAC ?13.11(c)(13)) which would terminate the Loan if construction was not completed within the four (4) year deadline to allow construction completion past the four (4) year deadline to July 1, 2023;
WHEREAS, in accordance with and pursuant to 10 TAC ?11.207 and 10 TAC ?13.1(c), on September 1, 2022 the Board approved a waiver of 10 TAC ?13.11(p)(11) (re-codified and then cited as 10 TAC ?13.11(c)(14)(L), and now cited as 10 TAC ?13.11(c)(14)(K)) and further granted the Owner an extension of the time period to request the final draw of construction loan funds past twenty-four (24) months to January 31, 2023 and to extend the time for the Department to disburse the final draw to July 1, 2023;
WHERAS, in accordance with and pursuant to 10 TAC ?13.13, on September 1, 2022 the Board further approved an additional extension of the Development Period to forty-two (42) months and an extension of the time period for the Department to issue the Closed Final Development Inspection Letter past thirty-six (36) months to December 31, 2022;
WHEREAS, Owner did not meet those deadlines; and
WHEREAS, Sierra Vista Senior Villas has completed construction and has been occupied, but the deadline to request the final draw of construction loan funds and the Development P...

Click here for full text